GREEN MOUNTAIN about how they do it . As members of the Considerate Constructors Scheme , T . Clarke has actively engaged with our neighbours during the construction to keep them updated and addressed feedback to minimise any disruption experienced .”
With the enablement works complete and moving into the M & E fit out stage , the project remains on track , and within budget .
Green Mountain ’ s pedigree in delivery is clear and is underpinned further by their recent 90MW build in 18 months in Norway for TikTok .
Prepared for AI and HPC workloads With the exponential growth and the seemingly unfettered investment in AI , demand for data centres will continue to increase . Some reports suggest a CAGR of 18 % to 2030 , making it critical that new data centre capacity is capable of dealing with the HPC workloads that are required .
Whereas some data centre operators are having to retrofit their existing infrastructure to become “ AI ready ”, LON-East ’ s technical specifications are designed to accommodate modern computing demands .
24 February 2025