MAINOVA WEBHOUSE its climate and specifications , in terms of permitting . “ Given our background , we could source enough plots , grid connections and source pipeline projects to allow us to grow the business in the Frankfurt region , we believe that this is where we have an edge over competition .”
This is the location of Mainova WebHouse ’ s first DC campus , the MWH01 .
Mainova WebHouse targets LEED Gold with sustainability measures Mainova WebHouse ’ s first campus consists of two buildings , the first building has a capacity of 20 megawatts and the second 10 megawatts IT load . They were originally designed as a co-location setup , but that changed with a tenant being one of the hyperscalers . Mainova Webhouse was able to accommodate the design requirements